News

 29 October 2018

The contractor has been selected for the “Implementation of C-ITS in the City of Brno” order, of the ENERGOVOD CZ, a.s. and CROSS Zlín, a.s. business alliance

29 April 2019

The contractor invited the purchaser (BKOM) to initiate acceptance procedure and completion of stage 1 under the Contract for Work (SoD)

13 – 20 May 2019

Individual tests have been carried out of the handed over RSU, OBU/RVU, BO.

12 June 2019

The designer’s supervision agrees with the handover of the system and initiation of stage 2.

27 June 2019

Complex tests took place at selected locations attended by the purchaser, seller and partners of the C-ROADS CZ project: Intens and CTU FTS.

10 July 2019

The acceptance and handover protocol was signed and the work accepted for use.

9 October 2019

Press conference - Teaching cars to communicate - more here

December 2019

At the supplier of the ordering system, the addition of C-ITS with PKI (system of signing and verification of broadcast messages, delivery date is 29 February 2020) and UC PTP (public transport preference to SSZ, delivery date is 31 March 2020).

26 February 2020

C-ITS BKOM has been tested extensively with the participation of C-ROADS partners. Based on long-term preparations for testing, the delivery dates of PKI and UC PTP will be postponed by approximately 30 days.


25 May 2020

A large-scale testing of C-ITS interoperability took place with the participation of partners within the C-ROADS project. The aim was to verify the interoperability of the DPMB (Dopravní podnik města Brna a.s.) and BKOM (Brněnské komunikace a.s.) systems, to verify the functionality of public transport preferences, and the compliance of broadcast messages with C-ROADS standards.